Return to Index
Operations Research Models and Methods
 
Computation Section
Subunit Dynamic Programming Examples
 - Sequence Solution

The solution of the well sequencing problem is found with the DP Solver add-in (dp_solver.xla). Click the Transfer to DP Solver at the top of the model page. Of the Solver forms, only the Transition List option is possible. The number of states is too large for either matrix format. The add-in automatically constructs the solver model. To find the optimum solution, click the Solve button at the top of the page.

 

We choose the Value approach for optimization. This number of states is too large for the Policy option. The Acyclic option could have been chosen since the network for this problem is acyclic. The Value option improves the policy at each iteration. It stops when two solutions have almost the same values. Since this problem is transient, it will terminate in a finite number of iterations.

  After five iterations, the optimum is found. Part of the solver worksheet is shown below for only a few of the 730 states. Starting in state 1, the optimum solution is to drill well 3. The State Value is the optimum value for the sequencing problem, 14.40296 millions. It is apparent that some drilling is recommended for this field even through the valuation of the individual wells are all less than zero.
  The remaining decisions of the sequence problem depend on the outcome of drilling well 3.

 

Recovering the Solution

A major stumbling block for stochastic dynamic programming is in recovering the optimum solution. Even when the system starts in a particular state, the uncertainty associated with transitions quickly brings other states into the solution. This problem is not so apparent in deterministic DP because the solution is usually a single path through the state space, and recovering that path is not too difficult.

The tables on the DP solution page completely describe all states and all transitions, so theoretically the states entering the solution can be discovered by tracing through the various tables. For example, starting at state 1 with no wells drilled, the state table reveals that the optimum decision index is 3. This information is in column M of the first row.

  From row 3 of the decision list we see that the solution involves drilling well 3, and the information regarding transitions is in column AM. The numbers in column AM give the last row of the transition list that pertains to the decision. For decision 3 we see that the transitions for decision 3 are in rows 5 and 6. The starting row is one greater that the last row for decision 2.
  Moving to rows 5 and 6 of the transition list we see that two transitions are defined, one for the dry result and one for the wet result. The transition probabilities for these events are in column AY. The next state for a transition is in column AZ, the dry transition is to state 28, and the wet transition is to state 55.
  The recovery process then returns to the state list to review states 28 and 55. The decisions in these states lead to yet other states in the solution. This recovery process is possible, but difficult.

 

Finding the Solution with Value Iterations

 

The add-in provides an easier way to discover the states involved in the optimum solution. In the dialog reached via the Solve button, we set the options as below.

Chose the Value iteration with a fixed policy (check Fix Policy Box). Near the bottom of the form, initialize the probabilities to set the probability of state 1 to the value 1. To see the results, select the All option, and Clear the iteration display by checking the box at the top. The results are stored on the Well States worksheet. Click the Hide zero Probs. button to show only states with nonzero probabilities.

On clicking OK the add-in evaluates the probability distribution of the states through the steps of the well drilling. The process stops when the last two steps have the same probability.

  Part of the worksheet is shown below. With this option the program sums the state probabilities as the iterations progress. The sums are in column A. When the process is complete, all states with zero probabilities are hidden. The result is a table showing only states that are visited during the process. The summed probabilities are not a proper distribution on the state space, because individual states may be visited several times. For example, the Final state is encountered several times in the example and it's probability sum is greater than 1.
 

The display above shows the state definitions and the state values and probabilities at termination. The state probabilities for each iteration are stored starting in column P. In the figures below, some columns are hidden for clarity. The initial state probabilities and the first two iterations are below. Step 0 shows the state values and probabilities after the initial solution has been imposed, but before any computational iterations. The probability vectors in columns T, W and Z show the state probabilities for each step. We see that starting in state 1, the next step has states 28 and 55 with probabilities 0.47 and 0.53, respectively. The next step moves to states 56 and 57. There is also has a 0.47 probability that drilling will terminate.

  Steps 4 through 6 are below. The program stops at step 6 because the results in step 5 and 6 are identical.
  Notice that the states visited do not include well 4. The process always terminates before well 4 is considered. Well 4 is not a viable candidate under any circumstance.
 
The figure shows the decision tree for the optimum solution. There is sufficient information from the reported results to construct this tree. (The figure was borrowed from the paper.)

 

Conclusion

 

This example illustrates that problems with fairly large state spaces can be modeled and solved with the DP add-ins. The solutions on this page were each obtained in about one minute of computation. The example also indicates an approach to other sequencing problems. The important distinction in this case is that the transition probabilities depend only on the set of wells already drilled and not the exact sequence of drilling. Of course the number of items that can be sequenced by this approach is small, since each additional item doubles the number of states.

 
  
Return to Top

tree roots

Operations Research Models and Methods
Internet
by Paul A. Jensen
Copyright 2004 - All rights reserved