Problems Section



Without Queues



With Queues

Subunit
Process Flow Analysis
- Board Manufacture

Facilities for populating printed circuit boards are generally configured as flow lines. A simplified version of a facility for board manufacture is shown in the figure. The first station is where raw boards are inspected and marked, and component kits are prepared. Let us assume that the orders arrive at the rate of 60 boards per hour and that, on average, 80 boards can be processed per hour. A certain fraction, 5%, must be recycled through this stage to correct defects, while 75% move on to the surface mount technology (SMT) center and the remaining 20% go to the through-hole center. Station 2 consists of 3 SMT robotic placement machines that can each process an average of 30 boards per hour. It receives input from both the preparation area and from outside customers. Station 3 has a single through-hole (T-H) machine that operates at an average rate of 20 boards per hour.

After the small components are placed on the boards, they all go to a manual workstation staffed by 8 operators who perform a preliminary inspection and attach large components, such as heat sinks and batteries. Each operator can process 15 boards per hour on average. Next, at station 5, the boards flow through a wave solder machine that has a capacity of 100 boards per hour. There are two solder machines operated in parallel. Boards are also cleaned and touched up at this stage. At station 6, testing on one of five parallel machines is conducted to look for opens and shorts, and to determine if the boards function correctly. The testing rate is 30 per hour. On average, 6% of the boards must return to station 5 for additional soldering and 12% to station 4 for rework. The remaining 82% pass all tests and are shipped.

Construct the process flow model for this situation. Find the utilization of each of the machines, total throughput time and WIP for the system.

Assume all interarrival times and service processes have exponential distributions with mean values determined by the rates given above. Add queues for each station. Find the utilization of each of the machines, total throughput time and WIP for the system.



  
Return to Top

tree roots

Operations Management / Industrial Engineering
Internet
by Paul A. Jensen
Copyright 2004 - All rights reserved

 

{dump}