Network Flow Programming Models |
|
-
Warehouse Location |
|
There are four possible sites for warehouses. The monthly equivalent
cost of construction at each site is $1000 per month plus a variable
cost of $5 per month per unit shipped. There are five customers
with demands (per month) and transportation costs ($ per unit)
as shown in the table.
|
Demanders
|
Warehouse
|
1
|
2
|
3
|
4
|
5
|
1
|
8
|
12
|
6
|
15
|
9
|
2
|
11
|
17
|
3
|
4
|
7
|
3
|
9
|
17
|
10
|
2
|
6
|
4
|
15
|
20
|
5
|
12
|
3
|
Demand
|
20
|
30
|
40
|
50
|
20
|
Assume warehouse capacities are limited to
shipments of 70 units per month. Solve the problem with a network
model with some integer arcs.
|
|